Sorry if this question has been asked. I am in the process of laying tile on my bathroom. Have never laid tile before. I got a Rigid wet tile saw (R4030) that works really well. Using 12x24 tiles. Already laid Schluter Ditra. Just got done dry-laying the tiles and ready to apply mortar. The floor is 12' x 10' with about 70% to be tiled. Since the tiles are now dry-laid in place I had planned on mortaring only a few tiles at a time. I plan to start at about the middle and continuing towards the back end leaving the path towards the entrance last. I don't think I can do all in one sitting so my question is how do I end the mortaring whenever I pause? And is my sequence of direction to tile ok? Thanks.