We are having our bathroom gutted and remodelled, including the addition of an exhaust fan. The walls shall be covered with tile.

What should I expect the sequence to be for the installation of electrical work, plumbing work, primary wall covering, bathroom fixtures, floor tile, and wall tile ?

Sometime in between, I must prep and paint the ceiling (after the contractor does the tape and spackling).

What is a realistic length of time for a (medium) bathroom to be redone ?

Thanks.
 

tbasc

Usenet Archive
Joined
Dec 6, 2004
Messages
918
Reaction score
0
Vince said:
We are having our bathroom gutted and remodelled, including the addition of an exhaust fan. The walls shall be covered with tile.

What should I expect the sequence to be for the installation of electrical work, plumbing work, primary wall covering, bathroom fixtures, floor tile, and wall tile ?

Sometime in between, I must prep and paint the ceiling (after the contractor does the tape and spackling).

What is a realistic length of time for a (medium) bathroom to be redone ?

Thanks.
You should ask your contractor about both sequence of work & the time allowed for your painting. Your contractor knows the existing conditions and his work force.
TB
 

Edwin Pawlowski

Usenet Archive
Joined
Sep 25, 2001
Messages
8,269
Reaction score
0
Vince said:
What should I expect the sequence to be for the installation of electrical work, plumbing work, primary wall covering, bathroom fixtures, floor tile, and wall tile ?
Electrical and rough pumbing can be done at the same time. Next is wall covering. Cabinets, tub/shower in place. The finish plubing and hookups are done after the cabinets and floor are in place.
Sometime in between, I must prep and paint the ceiling (after the contractor does the tape and spackling).
This can be done before other finishing. Not a big deal if you have to go back and touch up a smudge.
What is a realistic length of time for a (medium) bathroom to be redone ?
On TV, they build a house in a week. This requires some co-ordination and multiple visits by the plumber. I'd allow at least two weeks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Members online

No members online now.

Forum statistics

Threads
144,906
Messages
1,592,100
Members
59,482
Latest member
lisac

Latest Threads

Top